Kris Marsh

Start Date: October 1, 2004
Finish Date: June 22, 2005
Duration: 264d 17h
Report Date: February 23, 2005

Gantt Chart


*** Note: Gantt chart requires CSS capability. ***
WBS Name Work Week 40, 2004 Week 41, 2004 Week 42, 2004 Week 43, 2004 Week 44, 2004 Week 45, 2004 Week 46, 2004 Week 47, 2004 Week 48, 2004 Week 49, 2004 Week 50, 2004 Week 51, 2004 Week 52, 2004 Week 0, 2005 Week 1, 2005 Week 2, 2005 Week 3, 2005 Week 4, 2005 Week 5, 2005 Week 6, 2005 Week 7, 2005 Week 8, 2005 Week 9, 2005 Week 10, 2005 Week 11, 2005 Week 12, 2005 Week 13, 2005 Week 14, 2005 Week 15, 2005 Week 16, 2005 Week 17, 2005 Week 18, 2005 Week 19, 2005 Week 20, 2005 Week 21, 2005 Week 22, 2005 Week 23, 2005
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
1 Initial Document 15d
2 Planning 115d 5h
2.1 Research 115d 5h
2.2 Learning libraries 107d
2.3 Create Peripheral Systems 47d
3 Interim Document 11d 2h
4 Program 176d
4.1 GUI 83d
4.2 Main Engine 91d 2h
4.3 Basic Functionality 58d 6h
4.4 Extended Functionality 18d
5 Testing 113d
5.1 GUI 5d 2h
5.2 Main Engine 10d
5.3 Final Testing 20d
6 Dissertation 265d

Tasks

WBS Name Start Finish Work Priority Cost
1 Initial Document Oct 1 Oct 15 15d
2 Planning Oct 1 Jan 24 115d 5h
2.1 Research Oct 1 Jan 24 115d 5h
2.2 Learning libraries Oct 1 Jan 15 107d
2.3 Create Peripheral Systems Oct 21 Dec 7 47d
3 Interim Document Jan 24 Feb 4 11d 2h
4 Program Dec 7 Jun 1 176d
4.1 GUI Dec 7 Feb 28 83d
4.2 Main Engine Dec 16 Mar 17 91d 2h
4.3 Basic Functionality Mar 17 May 14 58d 6h
4.4 Extended Functionality May 14 Jun 1 18d
5 Testing Feb 28 Jun 21 113d
5.1 GUI Feb 28 Mar 6 5d 2h
5.2 Main Engine Mar 17 Mar 27 10d
5.3 Final Testing Jun 1 Jun 21 20d
6 Dissertation Oct 1 Jun 22 265d

Resources

Name Short name Type Group Email Cost